Casework and/or Laboratory Equipment
- Extent of each type of equipment, clearly distinguished from millwork, etc. (Use specification references.)
- Dimensions for principal elements of the work or a catalog number or key which establishes the dimensions and characteristics of the units.
- Differentiate between metal, wood, plastic laminate if more than one type is used and specified.
- Finish for each item unless all items are of one finish and specified as such in Project Manual.
- Special lighting with reference to fixture type (F2, etc.) and referenced to electrical plan or detail where fixture occurs.
- Locate and dimension (if pertinent) electrical items appearing on Casework elevations such as duplex receptacles, junction boxes, lighting, etc.
- Clarify which counters have splashbacks, in elevation and floor plan.
- Indicate upper cabinets, shelves, etc. in plan by dashed lines.
- Indicate furring and furring material over upper cabinets or shelf units, if applicable.
- Clearly distinguish between Plastic Laminate tops, "Lab Grade" tops, stainless steel tops, stone tops, etc. with appropriate "Specification Reference."
- Clearly indicate and distinguish between sinks, lavatories, equipment, etc. specified with tops or casework as opposed to those specified under Division 5 sections (Mechanical) by use of cross referencing and "Specifications Reference."
- "Drawing Title Designation" on all Casework and Laboratory Equipment elevations.
- Indicate proper clearances between counter top and cabinets or shelves above.
- Indicate locks on cabinets, drawers, etc., where required.
- Indicate special items such as label holders, etc. unless they are a part of the
unit specified.